Can My House Take a Second Storey?

On this page12 sections
- Why a second storey is a structural question first
- The five things a structural engineer checks
- Sydney soil: why the same house behaves differently in Ryde and Rooty Hill
- Brick veneer, double brick or timber: what each means for going up
- Weight: why a lighter upstairs can mean less work downstairs
- Warning signs you can check yourself
- When the answer is “yes, but”: the usual fixes
- What it costs to find out
- When the answer is no
- Before the engineer visits: checklist
- FAQs
- Sources and references
Your house has been holding up one roof for 40 or 50 years without complaint. Asking it to carry a whole extra floor is a fair question to put to it, and the engineer is the one who gets an honest answer. This guide is for owners thinking about going up who want to know their chances first: what the engineer looks at, what Sydney’s soil does, the warning signs you can check yourself, and the usual fixes when the answer is “yes, but”.
Why a second storey is a structural question first
A second floor roughly doubles the load on the existing house. Most single-storey Sydney homes built before the 1980s were designed to carry one floor and a roof, and nothing more. The footings were sized for that. So were the walls.
That’s why we put the engineer before the price on every second storey addition. A quote given before anyone has looked under the house is pricing a house that may not exist.
The five things a structural engineer checks
- The footings. Brick walls usually sit on strip footings. Timber floors sit on piers. Newer homes may sit on a slab. The engineer often digs a test hole beside a footing to see its depth, width and condition, because drawings from 1968 are rarely complete and sometimes optimistic.
- The soil. How much the ground moves as it wets and dries decides how much load the footings can safely take. More on Sydney soil below.
- The walls and load path. Which walls carry the roof now, and which will carry the new floor. Load has to travel in a clean line from the new roof down to the ground.
- The floor and ceiling structure. Existing ceiling joists were sized for plasterboard and insulation, not for beds, bookshelves and a teenager’s drum kit. The new level normally gets its own floor structure, designed by the engineer.
- The condition of what’s there. Termite damage, rot, past movement and old renovations that removed a wall they shouldn’t have. All of it has to be found before the price is fixed.
Around the second storey check sits the rest of how we build: foundations and slabs, bracing and how we build a second storey.
Sydney soil: why the same house behaves differently in Ryde and Rooty Hill
Australian Standard AS 2870 sorts sites by how much the ground surface can move as the soil wets and dries:
| Site class | What it means | Ground movement |
|---|---|---|
| A | Mostly sand and rock | Little or none |
| S | Slightly reactive clay | Up to 20mm |
| M | Moderately reactive clay or silt | 20 to 40mm |
| H1 | Highly reactive clay | 40 to 60mm |
| H2 | Very highly reactive clay | 60 to 75mm |
| E | Extremely reactive clay | Over 75mm |
| P | Problem site: fill, soft soil, trees, past demolition | Engineer decides |
Much of Western Sydney sits on clay soils weathered from Wianamatta shale. The NSW Government’s Blacktown soil landscape report describes the deep subsoils as moderately reactive, with high shrink-swell in places. In plain terms, the ground swells in a wet winter and shrinks in a dry summer, and the footings ride along.
The north isn’t automatically better. Shale clay caps many of the ridges on the North Shore and in the Hills, with sandstone in the gullies and slopes. Where the two meet, footings can move differently from one end of the house to the other. A soil test settles it.
Our opinion: take the piers down to shale or rock. An engineer might specify piers at around 2.5m when shale sits at 4m. Going deeper costs more in digging, concrete and steel, and it’s the one part of the house you can never get back to once it’s built on.
Brick veneer, double brick or timber: what each means for going up
- Brick veneer. The timber frame inside carries the roof. The brick skin outside mostly carries itself. Think of the brick as the raincoat and the frame as the skeleton. Upstairs loads go to the frame and down to the footings, so the engineer checks both.
- Double brick. The inner skin carries the load. Double brick can be strong, but it’s heavy and stiff, so it doesn’t forgive footings that move. Old cracks in double brick tell the engineer a lot.
- Timber frame on piers. Lighter, and easier to strengthen, because the engineer can add or upgrade piers and bearers under the floor.
We build double brick and timber-framed homes, depending on what the client wants. For an upper level on an existing house, the engineer’s design for your walls is what decides.
Weight: why a lighter upstairs can mean less work downstairs
The lighter the new level, the less the house underneath has to carry.
| Material | Approximate weight |
|---|---|
| Colorbond roof sheeting | About 4.4kg per m² (Lysaght) |
| Concrete roof tiles | About 44kg per m² |
| Terracotta roof tiles | About 48kg per m² |
| Fibre cement weatherboard cladding | About 11 to 21kg per m² |
| A single skin of face brick | Around 130 to 145kg per m², before mortar |
A tiled roof weighs about ten times as much as a Colorbond one, before battens and framing. That doesn’t mean tiles are off the table. Roof material is your choice. It means the engineer runs the numbers on what you pick, and a lighter upstairs can sometimes save a lot of strengthening downstairs.
Warning signs you can check yourself
Walk around the house before the engineer does. These are worth mentioning to them:
- Cracks in brickwork. Hairline cracks under 1mm are common and usually harmless. Under the NSW Guide to Standards and Tolerances, cracks of 5 to 15mm, or a group of cracks 3mm or wider, are a defect that needs repair.
- Doors that stick and windows that won’t slide. Often a sign the frame or footings have moved.
- Sloping floors. Put a marble on the floor. If it leaves the room in a hurry, tell the engineer.
- Cracks that open and close with the seasons. That points to reactive soil, often helped along by a leaking pipe, a downpipe that empties against the wall, or a big tree.
- Old termite damage or soft timber in the subfloor.
None of these automatically rules out a second storey. They tell the engineer where to look first. The NSW Government’s Guide to Standards and Tolerances explains how cracks are measured.
When the answer is “yes, but”: the usual fixes
This is the part of the job nobody puts on Instagram, and it’s where a second storey either lasts or doesn’t. Depending on what the engineer finds, the fixes usually include:
- New or deeper piers under existing walls, or underpinning existing strip footings
- Steel beams and posts that carry the new floor down to new footings, so the old walls don’t have to
- Strengthened walls and extra bracing in the existing house
- A lighter roof and cladding upstairs to cut the load
- Repairs to termite damage or rot before anything goes on top
These are priced after the engineer’s visit and listed in the quote. Our second storey cost guide shows how they sit outside the package price.
What it costs to find out
Finding out is cheap next to building on the wrong answer. Typical market ranges in NSW:
- Soil test and site classification: about $700 to $1,500
- Structural engineer’s inspection and report: about $400 to $2,000, depending on the house
- Full structural design for the addition: several thousand dollars
On our jobs, engineering sits inside the preliminaries of around $30,000 that cover design, engineering and council approvals, plus site set-up. During the build, the structural engineer inspects the work as well as the certifier, and you’re welcome to bring your own inspector at the key stages.
Tool: Extend or Build Up? Compare going up with extending out for the same space: cost, time and yard.
When the answer is no
Sometimes the engineer’s report says the house isn’t worth strengthening. Footings failing under most of the house, serious termite damage through the frame, or a slab that’s moved a long way all point the same way. Then the honest options are:
- Extend out at ground level instead, on new footings designed for the soil. See our home extension cost guide.
- Knock down and rebuild, which sometimes costs less than saving a tired house. Our custom homes page covers it.
We’d rather tell you that at the first meeting than after the drawings are done.
Before the engineer visits: checklist
- Original plans if you have them, and approvals for any past additions
- Photos of cracks, with rough widths and when you first noticed them
- Doors and windows that stick, and whether it’s worse in wet or dry months
- Termite history and any past inspection reports
- Where downpipes, drains and big trees sit near the house
- Clear access under the floor and into the roof space
- The roof material you’d like upstairs, so the engineer can allow for its weight
FAQs
Not every house, but most can. Roughly one in six needs significant extra spending first. A structural engineer’s inspection of the footings, walls and soil gives the answer.
Usually, yes. The inner timber frame carries the load, so the engineer checks the frame, the footings under it and the soil.
Yes, if the footings and walls can carry it. Double brick is heavy and doesn’t tolerate movement, so the engineer pays close attention to existing cracks and the soil.
A structural engineer exposes a footing or two, checks the soil classification and reviews the walls. Cracks, sticking doors and sloping floors are signs to point out to them.
Often, yes. It tells the engineer how reactive the soil is, which decides how much load the footings can take and whether they need strengthening.
An engineer’s inspection and report typically costs $400 to $2,000 in NSW, with a soil test around $700 to $1,500. Full structural design costs more.
Want the engineer’s view first? Request a consultation and we’ll get the engineer’s view first, or see what that looks like near you in Baulkham Hills and Carlingford.
Sources and references
- NSW Government (eSPADE): Blacktown soil landscape report
- NSW Government: Guide to Standards and Tolerances
- Lysaght: Custom Orb brochure (roof sheet weights)
- Monier: concrete tile data sheets (roof tile weights)
- Strava Group: Can my house take a second storey? and foundations and slabs